Outline planning permission or full planning permission – which do I need?

Find out when is the right time to use an outline planning application - and when a full planning application might be the better idea

16 January 2024
4 minutes read
Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.

Ever wondered about the difference between outline planning permission and full planning permission?

Very often landlords are confused about which application type works best for them. Does this sound like you?

In this article, we will cover outline vs full planning permission. you will learn the difference between outline and full planning permission. You will also learn the advantages and disadvantages of those application types so you can make an informed decision about your project.

An open book showcasing detailed landscape and site planning illustrations. One page features comprehensive site layout with pathways, building plots, and greenery, while the opposite page contains maps showing the project's location and context. The book is placed on a gray background, emphasising the architectural planning and design elements.

What is outline planning permission?

If you're an ambitious developer and have a decent amount of land you want to develop into housing, then you can get an idea of whether your proposal is acceptable to your local planning authority by applying for outline planning permission.

These are used by developers and investors on larger projects to see if the powers that be are likely to approve the overall principle of the project, and are often carried out as a cost- and effort-saving measure. As such, the development proposals are indicative, rather than detailed.

But remember: the plans still need to provide enough information about the building's overall proportions, access and effect on the surroundings –amongst other aspects – for the council to be able to make an informed decision on the development in principle.

An open booklet displaying detailed landscape designs and site planning. The left page features illustrations of different landscape features like water bodies and greenery, while the right page showcases a comprehensive site plan with pathways, building plots, and vegetation, reflecting the planning phase of a proposed development.

How can I apply for outline planning permission?

To complement the fairly basic detail of the outline planning permission, there is a further 'reserved matters' application. This application fills in the details that not submitted at the previous outline stage and covers a large spectrum of points, including:

  • external appearance
  • access and parking
  • landscaping
  • layout
  • size and scale

Essentially,  outline planning permission = indicative estimates, but by contrast, reserved matters application = actual details.

It's worth noting that the larger scale of these kinds of outline planning applications come with a caveat: the reserved matters application must be made within three years of the initial outline application. That being said, on applications for bigger, more complicated sites, the reserved matters applications can be done in phases.

An open architectural planning booklet showing detailed floor plans for a proposed building. The plans feature various rooms and spaces in different colors, indicating their specific functions, with legends and notes for reference.

What's the difference between an outline planning application and a full planning application?

Essentially, the answer of outline vs full planning permission is in the separation of the details.

The truth is the same amount of work and detail will have to go into an 'outline + reserved matters' application as into a 'full application'.

In essence, the difference is that developers prefer to know whether their project is likely to go ahead before they commit resources to it, and councils like to know about potential development in their area. Outline planning permission gives both sides 'wriggle room' so that the council can apply conditions – either restrictions or obligations – as necessary.

Construction machinery actively working on a development site with excavators and bulldozers preparing the land, surrounded by greenery and trees under a partly cloudy sky.

What conditions should you expect with outline planning permission?

The council might agree with the development in principle, but might restrict the use of the site – say, to purely residential – or require extra approval to confirm you've met certain requirements – eg, improved wheelchair access.

Similarly, there may be Section 106 agreements applicable – these are obligations from the council that are used to make a development more 'palatable'. These can include:

  • including affordable housing
  • making contributions to local travel, education, or leisure services
  • building or improving local roads and highways
  • improving essential site drainage
  • replacing affected wildlife habitat
  • providing open space, amenities or public art

It's worth remembering that these are arranged on a case-by-case basis by the council, so be prepared to negotiate and be flexible – goodwill goes a long way!

Close-up of a wooden stamp with a metal rim on a gray surface, leaving an 'Approved' imprint on a white document, representing the approval of planning permission for a development project.

Is there any way to guarantee outline application approval?

Nothing is ever 100% certain, but the more groundwork done when you make your application, the better. If you have a tricky site, then addressing any potential issues in your outline application makes the council much more likely to approve it. Examples of problems that might have to be dealt with include:

  • local ecology
  • trees
  • flood risk or drainage issues
  • other landscape matters

Let's not forget: putting these considerations into your application shows that you are serious about moving forward with the project (and also does some of the council's work for them!)

An open architectural planning booklet displaying floor plans for a building project in various stages. The left page shows a modern kitchen interior, while the right page contains floor plans of different building footprints, RIBA stages 1 to 3, with detailed notes and dimensions for reference.

What are the advantages of a full planning application?

Full planning applications are diligently put-together documents that provide information on every aspect of a development.

Whether it's the access, parking, use, layout, siting, dimensions, elevations, drainage, or the orientation (amongst others!) of the building, it must appear in these exhaustive documents.

Here’s the deal: given the amount of work, resources and expense that goes into a full application, these are best used when the principle of development is unlikely to be a problem – for example, if a development is similar to existing buildings in scale, materials and size.

The advantage of full planning applications is that – despite the initial spend – doing the legwork at the beginning generally makes your project more cost-effective. As a guideline for the full planning application process, pre-application advice is available from the council – but it is certainly no guarantee of approval.

In a nutshell: Outline vs full planning permission

If you're confident your development will be passed by the council, then you can get pre-application advice from the council and then proceed to a full planning application, getting the bulk of the work out of the way at the beginning. This will take around 6 to 9 months, depending on the case and the council.

If you're less certain (or want to sell the plot with partial planning permission), then your best bet is to go for outline planning permission (around 3 months in total) and then a reserved matters application (around 4 to 6 months in total).

Outline and Full Planning Permission Timescales

Outline and reserved matters applications

Pre-application advice and full planning application

Application preparation - up to 1 month

Pre-application preparation - up to 1 month

Outline Application - 8 to 13 weeks

Pre-application - 1 to 2 months

Reserved Matters application preparation - 2 to 3 months

Full application preparation - 2 to 3 months

Reserved Matters application - 8 to 13 weeks

Full application - 8 to 13 weeks

Outline Planning Permission timescales

How Urbanist Architecture can help you

Whether you have a plot of land you want to develop but first want to put feelers out, or if you're 99% sure it'll be approved, then we can help you.

With us, you can get the advice you need and make the process simpler, easier and quicker with our team of experts to help you, regardless of whether you need outline planning permission or a full planning application.

Ufuk Bahar, Founder and Managing Director of Urbanist Architecture
AUTHOR

Ufuk Bahar

Urbanist Architecture’s founder and managing director, Ufuk Bahar takes personal charge of some of our larger projects, focusing particularly on Green Belt developments, new-build flats and housing and high-end full refurbishments.

Send me a message
Or call me on
020 3793 7878

Write us a message

We look forward to learning how we can help you. Simply fill in the form below and someone on our team will respond to you at the earliest opportunity.

Have you considered how much the construction will cost?

Urbanist Architecture is committed to protecting your privacy, and we'll only use your information to deliver the services you requested. For more information, please review our privacy policy.

Some fields are incorrect.

Read next

The latest news, updates and expert views for ambitious, high-achieving and purpose-driven homeowners and property entrepreneurs.

Read next

The latest news, updates and expert views for ambitious, high-achieving and purpose-driven homeowners and property entrepreneurs.

Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Planning drawings: Here's what architects say about planning drawings
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Navigating the building control application process for high-risk buildings
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Wraparound extensions: How to design & build yours and get planning permission
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Close to home: Finding the best local builders near you
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
House extension cost in London: How to calculate yours [FREE breakdown spreadsheet template]
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Practical steps to design a successful mansard extension and get planning permission
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Labour’s housing revolution opens doors for developers
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Potential locations for Labour’s new towns
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
House flipping in England: Buy, renovate and sell
Read more
Image cover for the article: Rolled architectural plans displaying detailed landscape designs and site planning, laid out on a gray background. The designs include different landscape features such as water bodies, greenery, and pathways, showcasing the planning phase of a proposed development project.
Think big, build small: Expert design tips for tiny homes in the countryside
Read more

Ready to unlock the potential of your project?

We specialise in crafting creative design and planning strategies to unlock the hidden potential of developments, secure planning permission and deliver imaginative projects on tricky sites

Write us a message
Decorative image of an architect working
Call Message